Redevelopment Esplanade

General information

  • Start of the construction works: autumn 2023

  • Timeline: 2-3 years

Phase 1: Redevelopment of the N10 including a bicycle path between Caves St. Martin and Wueswee

  • Upgrade of the N10 (Route du Vin)
  • Construction of a bicycle path
  • Sewage system: implementation of the storm water sewage system (parking lot), including siphon connections
  • New water mains, low voltage electricity, public lighting (parking lot and crosswalks) and telecommunications
  • Creation of parking lots using ecological paving stones
  • Construction of the sidewalks, including earthworks, sidewalk box, paving of the sidewalks with concrete paving stones
  • Creation of green spaces between the N10 and the bicycle path
  • Supply and installation of new street lights (LED type) for the roadway, parking lots and crosswalks