Redevelopment Esplanade

Phase 1: Redevelopment of the N10 including a bicycle path between Caves St. Martin and Wueswee

  • Upgrade of the N10 (Route du Vin)
  • Construction of a bicycle path
  • Sewage system: implementation of the storm water sewage system (parking lot), including siphon connections
  • New water mains, low voltage electricity, public lighting (parking lot and crosswalks) and telecommunications
  • Creation of parking lots using ecological paving stones
  • Construction of the sidewalks, including earthworks, sidewalk box, paving of the sidewalks with concrete paving stones
  • Creation of green spaces between the N10 and the bicycle path
  • Supply and installation of new street lights (LED type) for the roadway, parking lots and crosswalks

 

Work currently underway – status 12.12.2024:

Redevelopment of the N10 and installation of a cycle path along the Esplanade

  • Completion of drainage works
  • Early 2025 – Work on various networks (water mains, telecommunications and electricity networks) within the pavement along the urban fabric